Update 22 June 2020

The asphalt works at the intersection will commence on Wednesday 24 June, weather permitting.

The works are expected to be completed within three days under the following arrangements:

  • Traffic control crews will be utilised to manage pedestrian and traffic movements
  • During low peak hours, between school drop off and pick up time , full intersection closure and detours will be set up.
  • During peak times works will be completed under stop and go, with 1 lane of traffic maintained on all streets at any time.
  • Road will be reinstated and given back to two way traffic flow at the end of each shift.

Delays are to be expected to the flow of traffic with the speed limit reduced to 40km while the works are underway.

Once this work is completed, traffic impact going forward will be minimised as the remainder of the work can be done behind barricades.