Project Update 1 May 2020

The last stage of the 450mm watermain renewal works were completed yesterday. Crews will now commence the road building activities.

Talis have started demolition works in the area in front of the shops and will next week begin forming kerb and gutter. The first stage of asphalt laying work will follow in the week after.

Traffic movements between Suttor, Mitre and Lambert Streets is enabled under traffic controlled conditions. Pedestrians will also need to follow pedestrian routes delineated by barrier fencing.

Parking for access to the shops is available in the carpark near the Scout Hall. Council is asking that motorists allow for possible delays when travelling through the intersection and to please follow signage and directions from staff on site.

Advertising:

A radio campaign is continuing to run on local radio to remind the community that businesses adjacent to the intersection remain open. For the latest project information visit the Bathurst YourSay website or if you prefer to talk to someone, please call 6333 6100.

Share Project Update 1 May 2020 on Facebook Share Project Update 1 May 2020 on Twitter Share Project Update 1 May 2020 on Linkedin Email Project Update 1 May 2020 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>