Information sessions on roundabout construction

Council will hold two drop-in information sessions on the construction of the roundabout at Suttor, Mitre and Lambert Streets on Thursday, 14 November.

The first drop-in session will be at the Upstairs Startup Hub from 12.00pm to 2.00pm and the second session will be at the Scout Hall in West Bathurst from 2.30pm to 4.30pm.

The roundabout is being built in response to community concerns and feedback about safety issues at the intersection. The construction process is a complex and lengthy project due to the design of the intersection and the number of underground services in the area. It is envisaged the project will take approximately nine months to complete.

The project will be conducted in stages. The first of which are outlined below:

Stage one
Carpark construction adjacent to the shops and water main works at the rear of the shops. The intersection will remain open under traffic control. Access between Coral Way and Suttor Street will be closed for the duration of the project.

Stage two
Water main works at the intersection. The intersection will remain open under traffic control. Stages one and two are expected to take approximately eight weeks.

Stage three
Road realignment and service relocation. Suttor and Mitre Streets will remain open under traffic control. Lambert Street will be fully closed to traffic. This is scheduled to occur during school holidays to minimise impact to traffic. This stage is expected to take approximately four weeks.

For information follow the Council Facebook page or call 6333 6100.


Share Information sessions on roundabout construction on Facebook Share Information sessions on roundabout construction on Twitter Share Information sessions on roundabout construction on Linkedin Email Information sessions on roundabout construction link