George and Howick St Roundabout Update 8 March

The project is progressing on schedule and is now nearing the final phases.

Crews have completed the excavation of the old pavement material this week. Early next week 1100 tonnes of lean mix concrete road pavement will be poured over the entire site. It will need to cure for seven days. While this is occurring, works will continue on the footpaths.

Provision for u-turns are available on all approaches. Pedestrians continue to have access to businesses, however there is some impact to parking near the work site and for those that fall within the work zone.

The temporary carpark at the old Clancy Motors site open. It can be accessed directly from Howick Street or from the RSL carpark. There are 35 spaces available for 2 hour parking to allow customers to access nearby businesses in George and Howick St while the work occurs.

Council is also advertising the full closure on local radio, along with a separate ad to advise that all businesses near the work site are open for business.

Share George and Howick St Roundabout Update 8 March on Facebook Share George and Howick St Roundabout Update 8 March on Twitter Share George and Howick St Roundabout Update 8 March on Linkedin Email George and Howick St Roundabout Update 8 March link

Consultation has concluded

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>