George and Howick St Roundabout Update 29 March
The final touches are being applied to the intersection which is expected to be open to traffic next week.
The crews are continuing work on the splitter islands, blisters line marking and signage.
Over the next few days the concreting in-fill will be applied to the blisters and pedestrian refuges will be constructed.
Provision for u-turns are available on all approaches. Pedestrians continue to have access to businesses, however there is some impact to parking near the work site and for those that fall within the work zone.
The temporary carpark at the old Clancy Motors site is open for the duration of the works. It can be accessed directly from Howick Street or from the RSL carpark. There are 35 spaces available for 2 hour parking to allow customers to access nearby businesses in George and Howick St while the work occurs.
The temporary carpark at the old Clancy Motors site is open for the duration of the works. It can be accessed directly from Howick Street or from the RSL carpark. There are 35 spaces available for 2 hour parking to allow customers to access nearby businesses in George and Howick St while the work occurs.
Share George and Howick St Roundabout Update 29 March on Facebook
Share George and Howick St Roundabout Update 29 March on Twitter
Share George and Howick St Roundabout Update 29 March on Linkedin
Email George and Howick St Roundabout Update 29 March link
Consultation has concluded